20” Overboard Line

Using Pipetech's unique Aqua Milling® System, a 20” overboard blocked sea dump line was successfully cleaned returning to its intended free flowing state.

Pipetech mobilised to clear a problematic overboard line which was blocked by 80-90% of hard scale through a series of bends.

Working alongside the client to determine the best practice method for cleaning and disposal of waste.

A Specialist Cleaning Supervisor mobilised to complete a site survey identifying full scope requirements and methodology prior to execution of workscope.

Challenges

Successfully managed to gain challenging under deck access to overboard line, tackling multiple 90° bends including an initial vertical lift of 4.9metres from point of entry

Achievements

■ All works completed without incident, maintaining Pipetech`s zero LTI record.
■ Workscope completed ahead of intended schedule.

Benefits

Safety – Fully contained remotely operated jetting system ensuring safety as priority
Time – Successfully cleaned within 12 working hours
Cost – Minimal impact on POB and plant hire period