Pipetech mobilised to the Preem refinery to clean a total of 10km of pipework.
The intricate pipeline systems included crude oil lines, condensate lines, torch systems and any other oil holding pipelines. The pipes were from ID 0,5 to 42 inches.
Phase one of the project required us to create a project management team, who assessed the scope of work. Using our unique problem solving process, we listened closely to understand the challenges of the project. During phase two, we were able to pre engineering work to fully contain each system using a flanged face assembly, tailored to fit any pipe entrance during cleaning, leaving no spillages or debris for removal. Because of this, the execution phase ran very smoothly with high standards of interface with the Preem Refinery and good communication throughout.
Challenges
- Large scope
- Short lead times
- Number of simultaneous activities
Achievements
- All works completed without incident, maintaining Pipetech`s zero LTI record.
- Work scope completed within intended schedule.
Benefits
Safety – Fully contained remotely system ensuring safe operation with no incidences
Time – Successfully cleaned beyond target
Cost – Minimal rigging and dismantling saves time and people